Yerba Buena Island Interchange Ramp

The phase II environmental site assessment was prepared by AGS, Inc. (AGS) for the Yerba Buena Island Ramps Improvement Project. The objective was to assess the potential contaminant levels in soils and groundwater that may be encountered during the ramps improvement project. The scope of work included initially completing a total of 17 borings. Soil samples were collected for chemical analysis. Subsequently, and to assess the extent of the lead impact on the shallow soil, additional 45 locations were sampled and analyzed for lead, between 0 and 0.6 meters (0 to 2 feet) below surface grade.

Categories
Geotechnical, Environmental

Location
San Francisco Bay Bridge, CA

Client
San Francisco County Transportation Authority (SFCTA)