Project Profile

SFPUC Alameda Siphon No. 4

Client
San Francisco Public Utilities Commission
Location
Northern California
Completed
2012
Project Cost
$65 million
Project Size
Collaborators

Black & Veatch (Joint Venture Partner)

The Alameda Siphon No. 4 Project involved the construction of a new 66-inch diameter pipeline that extends across Sunol Valley from the existing Coast Range Tunnel to the Irvington Tunnel. The new pipe includes a connection to the existing pipeline exiting the east portal upstream of the existing connections for Alameda Siphon No. 2 and No. 3; new chemical feed points, crossings of the Calaveras Fault and the Alameda Creek, and cross-connections to the existing three siphons, and the Irvington Tunnel at the west portal. The entire pipeline alignment is located in a seismic hazard zone.

AGS, as a Joint Venture Partner, was responsible for the design of a seismically resistant welded steel pipe, approximately 3,000 feet long and 66-inches in diameter that extends across Sunol Valley from the existing Coast Range Tunnel connecting to either the existing or new Irvington Tunnels.  

Significant elements of AGS’ scope included:

Pipeline

• Assistance to City staff in site improvements

• Design of pipeline and micro tunnel extending below Alameda Creek.

• Design of pipeline and micro tunnel extending below Alameda Creek.

• Design of (5) large underground valve vaults to resist large thrust loads, soil pressure, and dynamic soil loads.

• Design of a pipeline fault crossing.

Facilities

• Evaluation and seismic retrofit of (2) existing valve houses and underground valve vaults.

• Design of (4) new 20-foot high tower structures and horizontal frames to support vertical and horizontal ventilation ducts.

• Design of foundation structures to support miscellaneous mechanical buildings.

• Design of elevated steel platforms for the valve vaults.

• Design of equipment support structures.

Roadway and Retaining Walls

• Realignment of an approximately 1,000-foot section of Calaveras Road.

• Redesign of existing Alameda East Portal Road intersection.

• Geometric design of new intersection into Calaveras Road and miscellaneous access roads.

• Street improvements and storm drainage facilities, including hydrology and hydraulic calculations.

• Design of retaining walls employing soil nail, soldier pile, and lagging, interlocking blocks, etc. 

Geotechnical, Fault Crossing/Creek Crossing

• Investigation to explore and evaluate the subsurface conditions for pipeline design and construction.

• Assessments of fault rupture hazard, liquefaction potential, and landslide conditions.

• Analysis of aquifer characteristics.

• Particular emphasis was made to assist in the development of design parameters for the Calaveras Fault crossing and the Alameda Creek crossing.

AEP Security Structure– Antiterrorism

• Design of an arch and a dome steel structure to protect the portal from blast loads in a postulated explosive attack.

• Design of an elevated steel platform over the arch-and dome structure.

• Design of a foundation consisting of concrete wall/grade beam on concrete piles to support the arch- and- dome upper structure.

• Design of a concrete headwall to resist the blast loads over the portal.

Tunnel Design

The AS4 Project involved the construction of a new water transmission pipeline that extends across Sunol Valley from the existing Coast Range Tunnel (CRT) to a new Irvington Tunnel. The 96-inch diameter tunnel advanced underneath Alameda Creek, and cross-connections to the existing three siphons and the proposed new Irvington Tunnel. The Tunnel was excavated using a Tunneling Boring Machine(TBM) with pressure head capability.

No items found.